找回密码
 立即注册

QQ登录

只需一步,快速开始

查看: 442|回复: 7

首件确认如何做

[复制链接]
发表于 2023-10-23 10:17:05 | 显示全部楼层 |阅读模式

马上注册,结交更多好友,享用更多功能,让你轻松玩转质量管理社区。

您需要 登录 才可以下载或查看,没有账号?立即注册

×
过程改变
生产过程中,5M1E(人、机、料、法、环、测)中任何一个或多个生产要素发生改变,如人员的变动、设备的调整和维修、换料和换工装夹具、设计变更、停线等等

 楼主| 发表于 2023-10-23 10:18:04 | 显示全部楼层
Process change



During the production process, any one or more production factors in 5M1E (human, machine, material, method, environment, measurement) change, such as personnel changes, equipment adjustments and repairs, material and fixture changes, design changes, line stoppages, etc


 楼主| 发表于 2023-10-23 10:18:41 | 显示全部楼层
首件检验
对每个班次刚开始时或过程发生改变后,生产线加工的第一或前几件产品进行的检验。检验的数量,可以根据不同企业或客户的要求制定。
一般来说,至少需要对连续生产的3-5件产品进行检验,合格后方可继续加工后续产品。在设备或制造工序发生任何变化,以及每个工作班次开始加工前,都要严格进行首件检验

 楼主| 发表于 2023-10-23 10:19:19 | 显示全部楼层
First article inspection



Inspection of the first or first few products processed on the production line at the beginning of each shift or after process changes.

The quantity of inspections can be determined according to the requirements of different enterprises or customers.



Generally speaking, at least 3-5 consecutive products need to be inspected and qualified before continuing to process subsequent products.

Strict first article inspection is required before any changes occur to the equipment or manufacturing process, and before each work shift begins processing

 楼主| 发表于 2023-10-23 10:19:52 | 显示全部楼层
首件检验的时机/场合
1 . 每个工作班开始
2 . 更换操作者
3 . 更换或调整设备、工艺装备
4 . 更改技术条件、工艺方法和工艺参数
5 . 采用新材料或材料代用后

 楼主| 发表于 2023-10-23 10:20:26 | 显示全部楼层
Timing/occasion of first article inspection



1 Start of each work shift



2 Replace operator



3 Replace or adjust equipment and process equipment



4 Change technical conditions, process methods, and process parameters



5 After using new materials or material substitution

 楼主| 发表于 2023-10-23 10:21:05 | 显示全部楼层
首件检验的要求
首件检验采用三检制:自检、互检及专检。
送检的产品必须先由操作人员进行“自检”,然后再由班组长或同事进行“互检”,最后由检验员“专检”,确定合格后方可继续加工后续产品
首件检验不合格,需查明原因、采取措施,排除故障后重新进行加工、进行三检,直到合格后才可以定为首件

 楼主| 发表于 2023-10-23 10:21:38 | 显示全部楼层
Requirements for First Article Inspection



The first article inspection adopts a three inspection system: self inspection, mutual inspection, and special inspection.



The products submitted for inspection must first undergo a "self inspection" by the operator, followed by a "mutual inspection" by the team leader or colleagues, and finally a "special inspection" by the inspector. After confirming that they are qualified, subsequent products can be processed



If the first article inspection is not qualified, it is necessary to identify the cause, take measures, and eliminate the fault before re processing and conducting three inspections. Only after passing the inspection can it be classified as the first article


您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

手机版|小黑屋|QPDCA平台自律公约|QPDCA质量论坛 ( 苏ICP备18014265号-1 )

QPDCA质量论坛最好的质量管理论坛 GMT+8, 2024-5-19 02:57 , Processed in 0.123992 second(s), 17 queries , Gzip On.

无锡惠山区清华创新大厦901室0510-66880106

江苏佳成明威管理咨询有限公司 版权所有

快速回复 返回顶部 返回列表